New NIST Child Care Center:
-
The FY2009 appropriations included $7.2M for a new NIST Child Care Center
-
Will expand our capacity to 154 (currently 99), allow us to accept children at 6 weeks of age (currently 18 mos.), will have 3 infant/toddler, 2 twos, 4 preschool, 1 kindergarten and 1 school-age classroom
-
Larger classrooms, addition of a multi-purpose room, canopied access to playground areas, greater storage, enhanced administrative/staff areas, infant nursing room, etc.
-
New building will be 23,300 sq ft (current buildings are 6,057 sq ft)
-
Groundbreaking Occurred on August 24, 2010.
-
Preliminary schedule:
-
- Construction: Sept 2010 - Feb 2012
- Move-in/Licensure: May-June 2012
Construction Photos

Progress as of Nov 2011.

August 4, 2011: The brick work is almost complete, front side.

August 4, 2011: Back side of the new center.

August 4, 2011: Grading and paving of parking lot for new center.

May 16, 2011: Brick work begins.

May 16, 2011: Roofing work continues.

On March 16, 2011 the framing for the new center is well underway.

Grading of the site for the new center, Nov 2010.