Skip to main content
U.S. flag

An official website of the United States government

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

The Construction of the SURF III Magnet

The south backleg is guided into position on the lower yoke. The two backlegs support the upper yoke assembly and provide a return path for the magnetic flux generated by the magnet.

south backleg of the SURF III
Credit: NIST

One block of the upper yoke is cleaned and prepared for placement. Since these blocks rest on top of the backlegs, the lower face is the presicely machined surface and must be cleaned prior to placement.

Mitch cleaning one block of the upper yoke of the SURF III magnet.
Credit: NIST

The first block of the upper yoke is being prepared for installation. It will be joined by four others and bolted into a single assembly. This five-block construction is identical to the lower yoke. Assembling the upper yoke was much easier than the lower yoke since the backlegs provide a much flatter surface than the floor.

first block of the upper yoke of the SURF III
Credit: NIST

The final block of the upper yoke assembly is lowered into place. After aligning this block to the others, the five upper yoke blocks were bolted into a single piece weighing 68,000 kg (75 tons).

final block of the upper yoke assembly of the SURF III
Credit: NIST

The completed upper yoke rests on the backlegs. The lower pole piece can be seen in position in the middle of the magnet. On the floor, the upper pole awaits installation.

completed upper yoke of the SURF III
Credit: NIST

Both pole pieces have been installed. The poles have been aligned in the center of the magnet assembly to within 25 µm (0.001 in). Pictured on the left is Lee Greenler, the mechanical engineer who performed the detailed design of the SURF III magnet for the project prime contractor PSL Engineering and Instrumentation.

pole pieces of the SURF III
Credit: NIST

The yellow main coils have been installed around the pole pieces. The upper yoke assembly was moved aside and the lower main coil was placed around the lower pole. Then the upper main coil was placed in its location and the upper pole (on the yoke assembly) was lowered into the coil. In this picture, one portion of the lower yoke has been painted with a light blue rust-inhibiting paint.

yellow main coils of the SURF III
Credit: NIST

The final step of the magnet assembly process was the installation of the trim coils on the pole faces. These small coils will be used during injection to control eddy currents formed by ramping up the magnetic field. The mustard colored surfaces have been coated with primer, but not yet painted blue.

installation of the trim coils on the pole faces of the SURF III
Credit: NIST

This page is online for historical purposes and will not be updated. Any questions should be sent to rvest [at] nist.gov (Rob Vest).

Contacts

Created July 16, 2024, Updated July 17, 2024